Engineering and transport infrastructure

The hub's railway, energy and external supporting infrastructure, developed in sync with the project implementation and the development plans of Alatau City.

The G-Trans Service hub is one of the key growth points of Alatau City. The development of railway, engineering and transport infrastructure is synchronised with the project implementation and the city's development plans.

Railway infrastructure

FacilityParametersStatus
Railway connection to Kairat station1,332 mDocumentation developed, state review passed, construction begun
Railway connection to Zhetygen station121.5 mDocumentation developed, state review passed, construction begun
GTS connecting trackUnder designProject documentation development
The hub's railway connection scheme

The hub's railway connection scheme

Completed works

Construction and installation works began in June 2025.

  • Reconstruction of the 10 kV overhead line and fibre-optic communication links
  • Earthworks over a section of more than 4.5 km
  • Construction of the subgrade and track base
  • Preparation of the construction site

Power supply

FacilityParametersStatus
Phase 1 power supply line5 MW, 10 kVDocumentation and state review completed
Line lengthabout 9 kmDesign completed
Power supply

External infrastructure

External supporting infrastructure

The development of external road, energy and gas infrastructure is planned as part of the development of Alatau City.

InfrastructureParametersStatus
Roadsover 10 kmPlanned as part of the external infrastructure
Electricity (prospective)up to 100 MWPlanned as part of Alatau City development
Gas supplyup to 20,000 m³/hPlanned as part of Alatau City development